COMPLETED PROJECT 09Bondi, NSW

Apartment Concrete Awnings, Window Hoods & Façade Projection Remediation

Awnings, window hoods & façade projections remediation delivered at Bondi, NSW.

PROJECT VALUE$592,000
SCOPEAwnings, window hoods & façade projections
PROPERTY TYPECoastal Strata Apartment Building
COMPLETED26 Mar 2026

Project Overview

This Bondi, NSW project involved awnings, window hoods & façade projections. Works were delivered under specialist-access remediation conditions, with the repair programme focused on safe access, reinforcement treatment and durable concrete reinstatement.

LOCATIONBondi, NSW
DELIVERYSpecialist-access remediation
REPAIR SCOPEAwnings, window hoods & façade projections
ACCESSCoastal exposure, overhead repair zones and specialist access requirements shaped the staged delivery programme.

THE PROBLEM

Coastal exposure had accelerated reinforcement corrosion within projecting concrete awnings, window hoods and other exposed façade elements.

THE REPAIR

Deteriorated concrete was removed, reinforcement cleaned and treated, and original architectural profiles reconstructed using structural repair mortar.

THE OUTCOME

Damaged façade projections were reinstated while preserving their original profiles and addressing corrosion-related deterioration.

SITE CONDITIONS

Coastal exposure, overhead repair zones and specialist access requirements shaped the staged delivery programme.

See The Transformation

Drag the slider to compare the affected concrete with the completed remediation.

After repair — Apartment Concrete Awnings, Window Hoods & Façade Projection Remediation Before repair — Apartment Concrete Awnings, Window Hoods & Façade Projection Remediation BEFOREAFTER

A Controlled Remedial Process

Each project follows the actual repair requirements, access constraints and site conditions.

01

Inspection & Defect Mapping

Affected areas were inspected, mapped and confirmed so the repair extent could be planned before breakout.

02

Controlled Concrete Breakout

Unsound and delaminated concrete was removed back to a sound substrate while surrounding areas were protected.

03

Reinforcement Treatment

Exposed reinforcement was cleaned, assessed and treated, with replacement or augmentation completed where required.

04

Structural Reinstatement

Compatible structural repair mortar was placed and finished to reinstate the original concrete profile.

05

Protective Interfaces

Repair edges, interfaces and exposed surfaces were detailed to suit the surrounding structure and site conditions.

06

Final Inspection

Completed repair areas were checked for finish, continuity and compliance before the work zone was handed back.