Coastal Apartment Podium & Column Remediation
Podium, columns & beam edges remediation delivered at Dee Why, NSW.
Project Overview
This Dee Why, NSW project involved podium, columns & beam edges. Works were delivered under occupied-property staging conditions, with the repair programme focused on safe access, reinforcement treatment and durable concrete reinstatement.
THE PROBLEM
Cracking, rust staining and spalling affected podium soffits, columns and beam edges in the coastal environment.
THE REPAIR
Damaged concrete was removed, reinforcement cleaned and treated, then structural sections rebuilt with repair mortar.
THE OUTCOME
Podium, column and beam sections were reinstated while safe access was maintained around the occupied property.
SITE CONDITIONS
Coastal exposure and an occupied site required controlled access and durable repair detailing.
See The Transformation
Drag the slider to compare the affected concrete with the completed remediation.
A Controlled Remedial Process
Each project follows the actual repair requirements, access constraints and site conditions.
Inspection & Defect Mapping
Affected areas were inspected, mapped and confirmed so the repair extent could be planned before breakout.
Controlled Concrete Breakout
Unsound and delaminated concrete was removed back to a sound substrate while surrounding areas were protected.
Reinforcement Treatment
Exposed reinforcement was cleaned, assessed and treated, with replacement or augmentation completed where required.
Structural Reinstatement
Compatible structural repair mortar was placed and finished to reinstate the original concrete profile.
Protective Interfaces
Repair edges, interfaces and exposed surfaces were detailed to suit the surrounding structure and site conditions.
Final Inspection
Completed repair areas were checked for finish, continuity and compliance before the work zone was handed back.